Reduced time and, by the same token, the cost of the project is a crucial factor in contemporary construction. This article presents a method for the exact optimisation of a resource-constrained scheduling problem. Based on the Critical Path Method, graph theory and linear programming, an algorithm was developed and the FROPT program was written in Matlab to minimise the execution time of the task. By using the newly-created program, sample networks were calculated and the results were compared with results obtained by using the MS Project scheduling program (using approximation algorithm). The execution time obtained by using FROPT were on average 10% shorter than those obtained using MS Project. In selected cases the improvement in execution time reached 25%. A deterministic approach to the problem may shorten planned project times and bring financial benefits. Due to the exponential complexity of the algorithm, it is most useful in solving small or highly coherent networks. The algorithm and program may result in benefits not offered by commercial software for planners of building projects.
Sroka, B., & Radziszewska-Zielina, E. (2016). An exact solution for the resource-constrained construction scheduling problem. Engineering Structures and Technologies, 8(2), 71-78. https://doi.org/10.3846/2029882X.2016.1196916
Authors who publish with this journal agree to the following terms
that this article contains no violation of any existing copyright or other third party right or any material of a libelous, confidential, or otherwise unlawful nature, and that I will indemnify and keep indemnified the Editor and THE PUBLISHER against all claims and expenses (including legal costs and expenses) arising from any breach of this warranty and the other warranties on my behalf in this agreement;
that I have obtained permission for and acknowledged the source of any illustrations, diagrams or other material included in the article of which I am not the copyright owner.
on behalf of any co-authors, I agree to this work being published in Engineering Structures and Technologies as Open Access, and licenced under a Creative Commons Licence, 4.0 https://creativecommons.org/licenses/by/4.0/legalcode. This licence allows for the fullest distribution and re-use of the work for the benefit of scholarly information.
For authors that are not copyright owners in the work (for example government employees), please contact VILNIUS TECHto make alternative agreements.